A tie beam carries two genuinely independent actions at once — ordinary bending and shear from the wall load it supports, plus an axial tension force tying two foundations together against differential settlement — and CSA A23.3 requires the net axial tension to actually reduce the concrete's shear contribution, not just sit alongside it unchecked.
Every check above runs automatically inside the Structyze Tie Beam (Plinth Beam) module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.
The Example We'll Use
- Span 4.0 m, simply supported
- b × h = 230 × 300 mm, cover 40 mm
- Wall (dead) load 2.0 kN/m; live 0
- Axial tie force 50 kN
- Concrete f′c = 25 MPa, steel 400W
Working Through It
Bending and the tie force are checked independently. Factored moment Mf = 4.57(4)²/8 ≈ 9.1 kN·m works through to a required As of just 124 mm² — well below the minimum of 173 mm², so minimum steel governs the flexural bars.
The tie force itself is carried entirely by the longitudinal steel: Tr = φsAsfy = 0.85(800)(400) ≈ 272 kN against a factored demand Tf = 1.5(50) = 75 kN — comfortable, using the same 4–15M bars already sized for flexure.
Here's the CSA-specific step: because the beam is in net tension, Cl 11.3.6.2 requires reducing the concrete's shear contribution — roughly a 25% cut here, bringing Vc down to about 22 kN, still above the 9.1 kN demand, but a different (and lower) number than an ordinary beam in the same geometry would show.
What Governs, and Why
Deflection runs tightest at utilisation 0.83, with stirrup spacing close behind at 0.66. Flexure and axial tension both carry wide margin (0.22 and 0.28) precisely because the tie force is modest relative to the flexural capacity already provided — a beam with a larger design tie force could see the shear reduction actually become the governing check instead.
Where Structyze Takes Over
Every check above runs automatically inside the Structyze Tie Beam (Plinth Beam) module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.
For Tie Beam (Plinth Beam) and the rest of the full catalogue — 80+ components across RCC, Steel, Composite, Timber, Masonry and more, across 20+ design codes — buy the full Structyze desktop app or see everything it does on the Software page.
Quick FAQ
Why does axial tension reduce concrete shear capacity?
Concrete's shear resistance partly depends on aggregate interlock and the compression zone staying intact across a diagonal crack — net axial tension works against that mechanism by widening cracks and reducing the compression zone, so CSA A23.3's general method (or the conservative reduction used here) accounts for that weakening closely rather than ignoring it.
Is a tie force always required by code?
No — CSA A23.3 doesn't universally mandate a tie beam between foundations. It's typically a project-specific input driven by differential-settlement risk or, in higher seismic categories, by the code's own seismic foundation-tie provisions (Cl 21).
Final Thoughts
The net-tension shear reduction is the one CSA-specific wrinkle in an otherwise ordinary tie-beam calculation — easy to miss if you check bending and axial tension separately and never revisit the shear number.