A composite steel-concrete beam designed to Eurocode 4 (EN 1994-1-1) checks shear connector spacing using a specific uniform-spacing provision that has a direct counterpart in several other codes covered throughout this series' composite content, but with its own distinct set of allowable spacing limits.

Every check above runs automatically inside the Structyze Composite Beam module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

The Example We'll Use

  • Beam: IPE 400 steel section, f_y 275 MPa, composite with 130 mm concrete slab, f_ck 25 MPa, effective width 2.2 m
  • Span: 7.5 m, design moment M_Ed: 298 kN·m
  • Shear studs: 19 mm diameter headed studs

Working Through It

Full shear connection moment capacity, with the plastic neutral axis confirmed within the slab: M_pl,Rd = 340 kN·m. Utilization: 298/340 = 0.88.

Design shear resistance per stud, per EN 1994-1-1's stud capacity formula (taking the lesser of the stud shank shear-governed value and the concrete-crushing-governed value): the governing value here is 81 kN per stud.

Total longitudinal shear force for full shear connection: 1,560 kN. Required stud count along the half-span: 1560/81 = 19.3, rounded up to 20 studs (40 total for the full span).

Checking EN 1994-1-1's maximum stud spacing limit (6 times the slab thickness, or 800 mm, whichever is less, for this slab thickness): maximum spacing = 6 × 130 = 780 mm; with 20 studs distributed over the 3.75 m half-span, actual spacing of 188 mm comfortably satisfies this upper limit.

What Governs, and Why

Flexural capacity governs at utilization 0.88, with the stud layout satisfying both the strength requirement (adequate total stud count) and Eurocode 4's maximum spacing limit — a reminder that stud design isn't just a total-quantity calculation; even a layout with enough total studs can fail if those studs are spaced too far apart, since excessive spacing risks uneven shear flow transfer between widely spaced connection points along the beam's length.

Where Structyze Takes Over

Every check above runs automatically inside the Structyze Composite Beam module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

For Composite Beam and the rest of the full catalogue — 80+ components across RCC, Steel, Composite, Timber, Masonry and more, across 20+ design codes — buy the full Structyze desktop app or see everything it does on the Software page.

Quick FAQ

Why does Eurocode 4 cap maximum stud spacing even when total stud count is adequate?

Shear flow along a composite beam isn't perfectly uniform in a simplified sense near concentrated loads or points of stress concentration, so a maximum spacing limit ensures studs are distributed closely enough to reliably transfer shear at any point along the beam, not just in an averaged, total-count sense across the whole span.

Does the maximum spacing limit change for a thicker concrete slab?

Yes — since the limit is expressed partly as a multiple of slab thickness (6 times the thickness, capped at an absolute maximum), a thicker slab permits a somewhat wider maximum stud spacing, reflecting that a thicker slab can more effectively distribute shear flow between more widely spaced connection points.

Final Thoughts

A shear stud layout needs to satisfy two separate requirements, not one — adequate total quantity for strength, and adequate distribution for reliable shear flow transfer. Precisely why Eurocode 4's maximum spacing limit exists alongside the stud count calculation, not as a redundant check but as a genuinely separate one.