A cantilever slab's governing check is very often deflection, not bending strength — IS 456's span/depth ratio for a cantilever is far more restrictive than for a simply-supported or continuous slab, since there's no far support to help limit how far the free tip can droop.

Every check above runs automatically inside the Structyze RCC Cantilever Slab module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

The Example We'll Use

  • Cantilever span 1.5 m (balcony slab)
  • Slab thickness 150 mm, M25/Fe415
  • Superimposed dead load 1.5 kN/m², live load 3.0 kN/m² (balcony)
  • 1 m wide design strip

Working Through It

Design moment at the fixed support: factored UDL wu = 1.5(0.15 × 25 + 1.5) + 1.5(3.0) — roughly 11.8 kN/m² combined, giving Mu = wuL²/2 for a 1.5 m cantilever. A modest moment easily carried by a 150 mm slab with minimum-to-moderate reinforcement.

IS 456's basic span/depth ratio for a cantilever is just 7 (versus 20 for simply supported, 26 for continuous) — even after modification factors for tension steel percentage, a cantilever slab's allowable span/depth stays meaningfully tighter than any other slab support condition in this series.

For this 1.5 m span at 150 mm effective depth (roughly 125 mm after cover), the span/depth ratio comes out close to the modified limit — deflection control, not bending or shear strength, is what actually dictates the minimum practical thickness for a cantilever this length.

What Governs, and Why

Deflection control (span/depth ratio) governs the slab thickness selection, with bending and shear both showing wide margin at that thickness — the defining characteristic of cantilever slab design generally, where stiffness rather than strength usually sets the minimum practical depth.

Where Structyze Takes Over

Every check above runs automatically inside the Structyze RCC Cantilever Slab module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

For RCC Cantilever Slab and the rest of the full catalogue — 80+ components across RCC, Steel, Composite, Timber, Masonry and more, across 20+ design codes — buy the full Structyze desktop app or see everything it does on the Software page.

Quick FAQ

Why is the cantilever span/depth limit so much stricter than a simply-supported slab's?

IS 456's basic ratios (7 / 20 / 26 for cantilever / simply-supported / continuous) reflect how differently each support condition deflects under the same span and load — a cantilever has a free end with nothing opposing its rotation, so the same span produces meaningfully more deflection than a slab supported (or continuous) at both ends. The code compensates by demanding a proportionally deeper section for the same span length.

Does increasing the tension steel ratio help a deflection-governed cantilever slab?

Only within limits — IS 456's modification factor for span/depth does increase with more tension steel, up to a point, since more steel raises the cracked-section stiffness. But there's a practical ceiling: past a certain percentage the modification factor flattens out, and a truly deflection-governed slab usually needs more depth, not just more steel, to clear the limit economically.

Final Thoughts

A cantilever slab governed by deflection rather than strength is a useful case study in why span/depth ratio checks exist at all — a slab can pass every strength check and still be unacceptably springy in service if thickness alone were chosen by bending moment.