ACI 318 has no provisions at all for a pile's geotechnical axial or lateral capacity — that's IBC or AASHTO territory entirely. What ACI 318 actually governs is the reinforced-concrete shaft itself, checked simply as a short tied column.

Every check above runs automatically inside the Structyze Pile Foundation module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

The Example We'll Use

  • Pile 20 in diameter, 40 ft long, bored, fixed head
  • Soil: clay (13 ft), sand φ=32° (16 ft), sand φ=35°
  • Water table 10 ft below grade
  • Axial loads: dead 45 kip, live 22 kip
  • Lateral (factored) 9 kip
  • 8–#6 bars, #3 ties at 6 in; resistance factor φ = 0.40

Working Through It

Three genuinely different calculations combine here. The geotechnical axial capacity — Meyerhof end bearing plus API-style skin friction, reduced by an AASHTO-LRFD-style resistance factor φ ≈ 0.4 — gives an allowable of about 470 kip against the 89 kip factored demand (utilisation 0.19). The lateral capacity, from Broms' method, gives φHu ≈ 40 kip against 9 kip (utilisation 0.23).

Neither of those two checks is an ACI 318 provision at all — they're geotechnical calculations the module bundles in for completeness. The genuinely ACI 318 check is the structural shaft: φPn,max = 0.52[0.85(4)(314−3.52)+60(3.52)] ≈ 659 kip, using the identical tied-column axial cap formula from ACI 318 Cl 22.4.2.1, against the 89 kip factored demand (utilisation 0.14).

The steel ratio, 1.12% on the circular shaft section, sits comfortably within the 1%–8% column range required by the same clause.

What Governs, and Why

This pile is very lightly loaded — all three checks carry large margins, common when a pile is sized by construction practicality or a group-layout rule rather than by demand alone. Worth noting the scope limits explicitly: this is a single isolated pile only, with no group efficiency or downdrag effects included, and Broms' method here only considers the uppermost soil layer.

Where Structyze Takes Over

Every check above runs automatically inside the Structyze Pile Foundation module — this particular module is part of the full desktop catalogue rather than the free browser trial, since the trial only carries a curated flagship set. You can still try the free trial modules right now to see the same calculation style in action on RCC Beam, Column, Slab and a handful of others.

For Pile Foundation and the rest of the full catalogue — 80+ components across RCC, Steel, Composite, Timber, Masonry and more, across 20+ design codes — buy the full Structyze desktop app or see everything it does on the Software page.

Quick FAQ

Why does ACI 318 only check the shaft, not the soil capacity?

ACI 318 is a concrete design code, not a geotechnical one — pile axial and lateral geotechnical capacity is governed by IBC-referenced geotechnical methods (or AASHTO for bridge work), while ACI 318's role is limited to ensuring the reinforced-concrete shaft itself doesn't fail structurally under the load the geotechnical capacity allows it to carry.

What's missing from this single-pile check for a real project?

Group efficiency (piles in a group interact and can carry less per-pile than an isolated pile), downdrag from settling soil, and the shaft's own moment capacity (a separate input here, not computed) all need separate verification before a pile group design is complete.

Final Thoughts

A pile foundation check is really three calculations wearing one hat — geotechnical axial, geotechnical lateral, and structural shaft. And only the last of those three is actually an ACI 318 provision.